Plot 1-painting is almost complete, in the kitchen, appliances are now being fitted, Tiling is about to start in the bathroom, kitchen and WC. Plumbing has been completed ready for testing when services are connected. The Fireplace will be addressed next along with completing Electrics, the property is Secure and Alarmed for security, Service connection are as follows:- Gas completion on 18th May, Elec completion 15th May, Water completion 13th May, BT connection and re-routing work (Pole Cables and underground Ducts) completion is Estimated to be around the 25th May.
Plot 2-Painting has Started, Joinery second fix work is ongoing near completion, Appliances are being fitted in the Kitchen, Plumbing 2nd fix almost completed, Elec second fix started, The Property is Secure and Alarmed.
Work on the Driveway for both Plots is aprox. 40% complete and the Garages construction will start shortly.